PROJECTS
BAHAWALPUR
INTRODUCTION
Bahawalpur Lot covers 22% of the area and 11% of the total estimated population of Punjab Province and includes Bahawalnagar, Bahawalpur and Rahim Yar Khan Districts. All three districts share their Eastern Borders with India. From North Eastern corner to South Western corner, the districts of this lot share border with Okara, Pakpattan, Vehari, Lodhran, Multan, Muzaffargarh and Rajanpur Districts of Punjab Province and Ghotki District of Sind Province. This lot is part of Thal and Nara Deserts of Cholistan.
Total settlements (Muza) in Bahawalpur Lot are 3,817 with population 9.63 million, approximately. Roughly 25% of the muza are un-served that covers 3% of rural population of this lot. In some muza, the Population Census Organization has published population of muza equal to '0' or '-' or below 100 persons
Universal Service Fund and Telenor entered in the contract to provide basic telephony and data services to the mass population in un-served areas of Bahawalpur on September 22, 2008.
Auction Details:
Lot ID: | RTeS/Lot12-Bahawalpur/2008 |
Advertised On | 11th March 2008 |
Bidders Registered: | 1. Pakistan Mobile Communication Ltd. (PMCL - Mobilink) 2. Pakistan Telecommunication Company Limited (PTCL) 3. Telenor Pakistan Pvt. Ltd. 4. Warid Telecom Pvt. Ltd. |
Opening of Qualification & Services Proposals: | Following registered bidders submitted their Qualification & Services Proposals on 24th July 2008; 1. Pakistan Telecommunication Company Limited (PTCL) 2. Telenor Pakistan Pvt. Ltd. |
Financial Bid Opening of Technically Qualified Bidders: | Following bidders were declared Technically Qualified and their Financial Bids were opened on 05th August 2008. Subsidy requested by each bidder is as follows; 1 PTCL Pak Rs. 649,000,000/- 2 Telenor Pak Rs. 248,381,865/- |
Result | M/s Telenor Pakistan Pvt. Ltd. was declared as the lowest qualified bidder and contract, worth Pak Rs. 248,381,865/-, was signed with Telenor on 22nd September 2008. |
Current Status:
The project has been completed.
Mauzas |
PCOs |
Telecenters |
||||||
Contracted |
Covered |
Audited |
Contracted |
Covered |
Audited |
Contracted |
Covered |
Audited |
888 |
888 |
888 |
15 |
15 |
15 |
- |
- |
- |
For details regarding selection of Technical Auditor click here
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
22-Apr-2009 |
11-May-2009 |
22-May-2009 |
TA of Milestone 2 (50% Work) |
25-Jun-2009 |
07-July-2009 |
18-July-2009 |
TA of Milestone 3 (75% Work) |
29-July-2009 |
04-Aug-2009 |
23-Aug-2009 |
TA of Milestone 4 (100% Work) |
24-Aug-2009 |
01-Sep-2009 |
12-Sep-2009 |
Comments:
The project has been successfully completed and audited within the contracted timelines. However, due to the delay in receipt of funds, payment for the final project milestone was made to the SP in December, 2009.