PROJECTS

KHYBER-PAKHTUNKHWA-PACKAGE Map

KHYBER-PAKHTUNKHWA-PACKAGE

    • INTRODUCTION

  •  
  • In Khyber Pakhtunkhwa 619 kms OFC to be laid to connect 35 unconnected tehsil headquarters and major towns enroute.Universal Service Fund and PTCL entered in the contract to connect the unserved Tehsil Headquarters and major towns on March 8, 2018.
  •  
  •  Auction Details:

  •  
  •  

    Package ID: 

    USF/SP/OpticFibre/2017/Khyber-Pakhtunkhwa

    Advertised On:

      8th May 2017

    Bidders Registered:

    1.  LinkdotNet
    2.  Pakistan Telecommunication Company Limited (PTCL)
    3.  Sharp Communication Pvt. Ltd.

    4.  Wateen Telecom Limited

    5.  Wi-Tribe Pakistan Limited

    Opening of Qualification & Services Proposals:

     

    Following registered bidders submitted their Qualification & Services and Subsidy Proposals on 6th October 2017;

                       

    1.  Pakistan Telecommunication Company Limited (PTCL)

    2.  Wi-Tribe Pakistan Limited (did not submit bid bond, bid rejected)

    Financial Bid Opening of Technically Qualified Bidders:

     

    PTCL was declared Technically Qualified and Financial Bid was opened on 21st November 2017. Subsidy requested is as follows;

     

    1- PTCL   

    800,000,000/-

     

     

     

     

    Result:

    PTCL was declared as the lowest qualified bidder and contract, worth Pak Rs. 800,000,000/-, was signed with PTCL on 8th March 2018.

    Current Status:

     

    Tehsil+Towns 

    Length of Optic Fibre (in kms)

    Operator

    Contracted

    Connected

    Audited

    Contracted

    Laid

    Audited

    PTCL

    35

    35

    35

    646

    646

    646

     Technical Audit:
  •  
  •  

    Offer   Date  

    Audit Start Date

    Audit Completion Date

     Mile stone 1 (25% of work)

     18-Jun-2019

     19-Jun-2019

     22-Jun-2019

      Mile stone 2 (50% of work)

     11-Sep-2019

     04-Oct-2019

     10-Oct-2019

      Mile stone 3 (75% of work)

     10-Oct-2019

     11-Oct-2019

     14-Oct-2019

      Mile stone 4 (100% of work)

     17-Dec-2019

     30-Dec-2019

     03-Jan-2020

    Comments:

    Information Package

    Information Package can be downloaded from here