NG-BSD Pishin Lot aims to provide coverage to Unserved/Underserved mauzas in the districts of Pishin, Quetta and Killa Abdulah. A total of 378 mauzas are to be provided Broadband Internet Services. Out of these, 290 mauzas are unserved with regards to voice telephony services and hence will be provided both Voice as well as Broadband Internet Services, whereas 88 underserved mauzas are being targeted for provision of Broadband Internet Services.
Universal Service Fund and Pakistan Mobile Communications Ltd. (JAZZ) entered in the contract to provide basic telephony and data services to the mass population in un/under-served areas of NG-BSD Pishin Lot on 22nd April 2021.
Package ID:
|
NG-BSD/LOT23-PISHIN/2020
|
|||||||||||||||
Advertised On:
|
12th July 2020
|
|||||||||||||||
Bidders Registered:
|
1. CMPak Ltd.
2. Pak Telecom Mobile Limited.
3. Pakistan Mobile Communication Limited.
4. Telenor Pakistan (Pvt) Ltd.
|
|||||||||||||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 15th Feb 2021:
1. CMPak Ltd.
2. Pak Telecom Mobile Limited.
3. Pakistan Mobile Communication Limited.
4. Telenor Pakistan (Pvt) Ltd.
|
|||||||||||||||
Financial Bid Opening of Technically Qualified Bidders:
|
All four bidders were declared Technically Qualified and Financial Bid was opened on 1st Mar 2021. Subsidy requested is as follows:
|
|||||||||||||||
Result:
|
PMCL was declared as the lowest qualified bidder and contract, worth Pak Rupees 1,319,809,195/- was signed with PMCL on 22nd April 2021.
|
Current Status:
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
12-May-2023 | 17-May-2023 | 27-May-2023 |
TA of Milestone 2 (50% Work) |
20-May-2024 | 10-June-2024 | 05-Aug-2024 |
TA of Milestone 3 (75% Work) |
|||
TA of Milestone 4 (100% Work) |
Mauzas: |
||
Contracted |
Covered |
Audited |
378 |
163 |