PROJECTS
LOT22-SHIKARPUR
INTRODUCTION
NG-BSD Shikarpur Lot aims to provide coverage to Unserved/Underserved mauzas in the districts of Shikarpur, Jacobabad and Kashmore. A total of 271 mauzas are to be provided Broadband Internet Services. Out of these, 26 mauzas are unserved with regards to voice telephony services and hence will be provided both Voice as well as Broadband Internet Services, whereas 245 underserved mauzas are being targeted for provision of Broadband Internet Services.
Universal Service Fund and Pakistan Mobile Communications Ltd. (JAZZ) entered in the contract to provide basic telephony and data services to the mass population in un/under-served areas of NG-BSD Shikarpur Lot on 22nd April 2021.
Package ID:
|
NG-BSD/LOT22-SHIKARPUR/2020
|
||||||
Advertised On:
|
12th July 2020
|
||||||
Bidders Registered:
|
1. CMPak Ltd.
2. Pak Telecom Mobile Limited.
3. Pakistan Mobile Communication Limited.
4. Telenor Pakistan (Pvt) Ltd.
|
||||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 25th Jan 2021:
1. Pak Telecom Mobile Limited.
2. Pakistan Mobile Communication Limited.
3. Telenor Pakistan (Pvt) Ltd.
|
||||||
Financial Bid Opening of Technically Qualified Bidders:
|
Following bidders were declared Technically Qualified and Financial Bid was opened on 19th Feb 2021. Subsidy requested is as follows:
|
||||||
Result:
|
PMCL was declared as the lowest qualified bidder and contract, worth Pak Rupees 344,190,302/- was signed with PMCL on 22nd April 2021.
|
Current Status
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% work) |
31-Mar-2022 | 14-Apr-2022 | 23-Apr-2022 |
TA of Milestone 2 (50% work) |
25-May-2022 | 28-May-2022 | 02-June-2022 |
TA of Milestone 3 (75% Work) |
09-Jun-2022 | 15-Jun-2022 | 19 June 202 |
TA of Milestone 4 (100% Work) |
25-Jul-2022 | 30-Jul-2022 | 02-Aug-2022 |
Mauzas
Contracted |
Covered |
Audited |
271 |
271 |
271 |