PROJECTS
MANSEHRA
INTRODUCTION
Mansehra Lot covers roughly 20% of the area of NWFP in the North-East and has 5 districts (Abbottabad, Batagram, Haripur, Kohistan and Mansehra) and 12 tehsils. This lot is bounded by Northern Areas in the North, Azad Jammu and Kashmir in the East, Rawalpindi, Islamabad and Attock Districts in the South, Swabi, Buner and Shangla Districts in the West and Swat District in the North-West
Total settlements (Muza) in this lot are 2,152 with population ca. 4.03 million. In some muzas, the Population Census Organization has published population of muza equal to '0' or '-' or below 100 persons.
Universal Service Fund and PTCL entered in the contract to provide basic telephony and data services to the mass population in un-served areas of Mansehra on June 24, 2008. A subsidy of Rs. 300 Million is being provided to PTCL for this rural telecom project.
Auction Detail:
Lot ID:
|
RTeS/Lot07-Mansehra/2008 |
Advertised On: | 11th March 2008 |
Bidders Registered: | 1. Pakistan Mobile Communication Ltd. (PMCL - Mobilink) 2. Pakistan Telecommunication Company Limited (PTCL) 3. Telenor Pakistan Pvt. Ltd. 4. Warid Telecom Pvt. Ltd. |
Opening of Qualification & Services Proposals: | Following registered bidders submitted their Qualification & Services Proposals on 26th May 2008;
1. Pakistan Mobile Communication Ltd. (PMCL - Mobilink) |
Financial Bid Opening of Technically Qualified Bidders: |
Following bidders were declared Technically Qualified and their Financial Bids were opened on 12th June 2008. Subsidy requested by each bidder is as follows; 1. PMCL (Mobilink) Withdrew its proposal |
Result: | M/s Pakistan Telecommunication Company Limited was declared as the lowest qualified bidder and contract, worth Pak Rs. 300,000,000/-, was signed with PTCL on 24th June 2008. |
Current Status:
Mauzas |
PCOs |
Telecenters |
||||||
Contracted |
Covered |
Audited |
Contracted |
Covered |
Audited |
Contracted |
Covered |
Audited |
631 |
631 |
631 |
113 |
57 |
57 |
1 |
1 |
1 |
For details regarding selection of Technical Auditor click here
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
22-Dec-2009 |
29-Dec-2009 |
12-Jan-2010 |
TA of Milestone 2 (50% Work) |
24-May-2010 |
03-Jun-2010 |
16-June-2010 |
TA of Milestone 3 (75% Work) |
- |
- |
- |
TA of Milestone 4 (100% Work) |
- |
- |
- |
Comments:
Technical audit of 2nd project implementation milestone has been completed however acheivement of the Miliestone could not be verfied due to some major snags. Currently snag removal is in progress.
Fruthermore Project is delayed due to Force Majeure events resulting from the seucrity operation in Malakand region that fall under this Lot and in the area of Kala Dhaka. Project is expetced to close by the end of year 2010.
Information Package |
Information Package can be downloaded from here. (If you don't have WinZip, please download from here) |