PROJECTS

NASIRABAD Map

NASIRABAD

  • INTRODUCTION:

     

    Nasirabad Lot covers roughly 5% of the area of Baluchistan in the Central East and has 4 districts (Bolan, Jaffarabad, Jhal Magsi and Nasirabad) and 7 tehsils. This lot is bounded by Larkana and Jacobabad districts in the South East, Dera Bugti and Kohlu districts in the North East, Sibi district in North and North East, Mastung district in the North West, and Khuzdar and Kalat districts in the West. Generally, Nasirabad Lot has an arid climate with moist cold winters and hot dry summers. 648 muzas and un-served population of around 487,000 people will benefit from this rural telecom project.

     

    Auction Detail

     

    Lot ID:

    RTeS/Lot11-Nasirabad/2009

    Advertised On:

    26th February 2009

    Bidders Registered:

    1. CMPak Ltd.

    2. Pakistan Mobile Communication Ltd. (PMCL - Mobilink)

    3. Pakistan Telecommunication Company Limited (PTCL)

    4. Telenor Pakistan Pvt. Ltd.

    5. Warid Telecom Pvt. Ltd.

    Opening of Qualification & Services Proposals:

    Following registered bidder submitted its Qualification & Services Proposals on 12th June 2009;

    1. CMPak Ltd.

    Financial Bid Opening of Technically Qualified Bidders:

    CMPak was declared Technically Qualified and Financial Bid was opened on 3rd July 2009. Subsidy requested is as follows;

    1.CMPak Pak Rs. 1,572,745,714/-

    Result:

    M/s CMPak Limited was declared as the qualified bidder and contract, worth Pak Rs. 1,572,745,714/-, was signed with CMPak on 28th July 2009.

     

    Current Status

    The project is in progress.

     

    Mauzas

    PCOs

    Telecenters

    Contracted

    Covered

    Audited

    Contracted

    Covered

    Audited

    Contracted

    Covered

    Audited

    616

    616

    616

    53

    53

    53

    3

    3

    3

    Technical Audit

    For details regarding selection of Technical Auditor click here

     

     

    Offer Date

    Audit Start Date

    Audit Completion Date

    TA of Milestone 1 (25% Work)

    16-Apr-2010

    02-Jun-2010

    16-Jun-2010

    TA of Milestone 2 (50% Work)

    15-Mar-2012

    08-Feb-2012

    27-Feb-2013

    TA of Milestone 3 (75% Work)

    15-Mar-2012

    08-Feb-2012

    27-Feb-2013

    TA of Milestone 4 (100% Work)

    24-Apr-2013

    08-Jun-2013

    20-Jun-2013

     

    Information Package

    Information Package can be downloaded from here.

    For WinZip Format click here. 

    For WinRaR Format Click here

    (If you don't have WinZip, please download from here)
    (If you don't have WinRaR, please download from here)