PROJECTS
OFC-UC-KP-LOT18
Introduction:
This project targets 37 unserved Union Councils/Towns in the districts of Bannu and Lakki Marwat with unserved population of 1,035,881. Universal Service Fund and Dancom (Pvt) Ltd. entered in the contract to connect the unserved Union Councils/Towns on 9th January 2023 (effective since 18th October 2022).
Auction Details:
Package ID: |
USF/SP/OpticFiber/OFC-UC-KP-LOT18 |
||||||||
Advertised On: |
14th February 2022 |
||||||||
Bidders Registered: |
1. Pakistan Telecommunication Company Limited (PTCL) 2. CMPAK (Pvt) Ltd. 3. LinkdotNet Telecom (Pvt) Ltd. 4. Dancom (Pvt) Ltd. |
||||||||
Opening of Qualification & Services Proposals:
|
Following registered bidder submitted the Qualification & Services and Subsidy Proposals on 26th May 2022: 1. Pakistan Telecommunication Company Limited (PTCL) 2. Dancom (Pvt) Ltd. |
||||||||
Financial Bid Opening of Technically Qualified Bidders:
|
Following bidders were declared Technically Qualified and Financial Bid was opened on 22nd June 2022. Subsidy requested is as follows:
|
||||||||
Result: |
Dancom (Pvt) Ltd. was declared as the lowest qualified bidder and contract, worth Pak Rs. 1,239,537,831/-, was signed with Dancom (Pvt) Ltd. on 9th January 2023 (effective since 18th October 2022). |
Current Status:
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
22-Nov-2023 | 27-Nov-2023 | 29-Nov-2023 |
TA of Milestone 2 (50% Work) |
19-Jan-2024 | 26-Jan-2024 | 31-Jan-2024 |
TA of Milestone 3 (75% Work) |
20-Aug-2024 | 02-Sep-2024 | 06-Sep-2024 |
TA of Milestone 4 (100% Work) |
Mauzas: |
||
Contracted |
Covered |
Audited |
387 | 324 | 324 |