OFC-UC-PB-LOT14
Introduction:
This project targets 47 unserved Union Councils/Towns in the district of Attock with unserved population of 922,935. Universal Service Fund and Nayatel entered in the contract to connect the unserved Union Councils/Towns on 19th October 2022.
Auction Details:
Package ID: |
USF/SP/OpticFiber/OFC-UC-PB-LOT14 |
||||||
Advertised On: |
8th July 2021 |
||||||
Bidders Registered: |
1. Pakistan Telecommunication Company Limited (PTCL) 2. CMPAK (Pvt) Ltd. 3. Nayatel (Pvt) Ltd. 4. Dancom Pakistan (Pvt) Ltd. |
||||||
Opening of Qualification & Services Proposals:
|
Following registered bidder submitted the Qualification & Services and Subsidy Proposals on 16th February 2022: 1. Nayatel (Pvt) Ltd |
||||||
Financial Bid Opening of Technically Qualified Bidders:
|
Nayatel was declared Technically Qualified and Financial Bid was opened on 8th March 2022. Subsidy requested is as follows:
|
||||||
Result: |
Nayatel was declared as the lowest qualified bidder and contract, worth Pak Rs. 2,693,000,000/-, was signed with Nayatel on 19th October 2022. |
Current Status:
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
16-Aug-2023 | 04-Sep-2023 | 06-Sep-2023 |
TA of Milestone 2 (50% Work) |
24-Nov-2023 | 11-Dec-2023 | 14-Dec-2023 |
TA of Milestone 3 (75% Work) |
|||
TA of Milestone 4 (100% Work) |
Mauzas: |
||
Contracted |
Covered |
Audited |
570 | 298.872 | 298.872 |