NG-BSD SIALKOT Lot aims to provide coverage to un/underserved mauzas in the districts of Sialkot, Narowal and Gujrat. A total of 232 mauzas are to be provided voice and high-speed broadband internet services. Out of these, 12 mauzas are unserved with regards to voice telephony services and hence will be provided both Voice as well as Broadband Internet Services, whereas 220 underserved mauzas are being targeted for provision of Broadband Internet Services.
Universal Service Fund and PMCL Pakistan entered in the contract to provide voice and high-speed broadband internet services to the mass population in un/underserved areas of NG-BSD Sialkot Lot on 22nd June 2022.
AUCTION DETAILS
Package ID: |
NG-BSD/Lot 42-Sialkot/2021 |
||||||
Advertised On: |
08th July 2021 |
||||||
Bidders Registered: |
1. CM Pak Ltd. 2. Pak Telecom Mobile Limited. 3. Pakistan Mobile Communication Limited. 4. Telenor Pakistan (Pvt) Ltd. |
||||||
Opening of Qualification & Services Proposals:
|
Following registered bidders submitted the Qualification & Services and Subsidy Proposals on 11th April 2022: 1. Telenor Pakistan (Pvt) Ltd. 2. Pakistan Mobile Communication Limited. |
||||||
Financial Bid Opening of Technically Qualified Bidders:
|
Following bidders were declared Technically Qualified and Financial Bids were opened on 25th April 2022. Subsidy requested is as follows:
|
||||||
Result: |
PMCL was declared as the lowest qualified bidder and contract, worth Pak Rupees 624,802,198/- was signed with PMCL on 22nd June 2022. |
Current Status:
Technical Audit |
Offer Date |
Audit Start Date |
Audit Completion Date |
TA of Milestone 1 (25% Work) |
21-Sep-2023 | -2-Oct-2023 | 08-Oct-2023 |
TA of Milestone 2 (50% Work) |
13-Dec-2023 | 22-DEc-2023 | 25-Dec-2023 |
TA of Milestone 3 (75% Work) |
|||
TA of Milestone 4 (100% Work) |
Mauzas: |
||
Contracted |
Covered |
Audited |
232 | 81 | 81 |